Contractors warned on safety,
target
Negros Chronicle, August 30, 2009

Image Courtesy of Negros Chronicle
|
|
Road contractors who do not comply
with all requirements and give inconvenience to the taxpaying
public will not be considered in the future road construction
projects.
Without necessarily naming them,
Second District Rep. George Arnaiz warned contractors of the P480
million road projects implemented in various cities and towns
to ensure the safety and convenience of the motoring public passing
through their project sites and keep up with the target date of
completion or it will be difficult for them to win in the biddings
next year.
Erring construction firms are reminded that they
are supposed not only to provide their laborers safety boots and
gloves but to purchase and put up signages, barricades, including
yellow tapes, blinking lights as well as hire a medical aid worker
and part-time safety practitioner and traffic enforcers for both
ends of the roads that are under rehabilitation. This is provided
so in the program of work the costs of which the firms have included
in the total contract price paid lump sum by the government.
Engr. Edna Ravelo, Chief of the Planning and
Design Office, appealed to the contractors to employ these safety
and medical laborers and purchase early warning devices, which
“they can after all use in future projects.”
Of the thirteen road concreting projects, two
have been completed and only five are facing delay for a number
of reasons namely: intervention of some local government units,
delay of the completion of Polo Bridge in Tanjay City and problems
with the Department of Environment and Natural Resources.
The projects facing delays are: Daro-Bunao Road
by Bigfoot Construction; CAB-Sta. Cruz Road, Tanjay City; Calo
Road Section, San Jose; San Jose Road Section, San Jose and Buswang
Road Section, Amlan.
Those already completed are Ajong Road, Sibulan,
P 10.5 million by Bigfoot Construction and Access Road Dumaguete
Airport for P 9.6 million by HLJ Construction.
Citizens have become increasingly vocal in criticizing
the contractors and concerned officials for the apparent delay,
inconvenience and lack of safety regulations observed in the ongoing
rehabilitation and concreting of roads.
Arnaiz, who was instrumental in securing the
funds for the district, admits that “some contractors have
committed violations,” particularly in the area of safety
and health for both motorists and construction workers. “I
have repeatedly called their attention and warned them,”
stressed Arnaiz.
However, the neophyte solon concedes, he “can’t
stop the contractors now because the projects will just incur
more delays.”
He also admits some contractors are behind the
agreed schedule of completion but vows to ensure that all ongoing
projects will be finished by December 2010.
On August 19, 2009,
Atty. Mikhail Lee L. Maxino, Director of the Salonga Law Center
wrote Governor Emilio Macias II to elicit answers as to what
his office can do to improve road safety in project sites, speed
up work and mitigate public convenience. Macias’
response letter was received by some quarters with disbelief
and disenchantment when the governor underscored his “non-involvement
and absence of control over these ongoing projects.”
Macias counseled those seeking relief to address
their questions instead to the Office of the District Engineer
of the Department of Public Works and Highways claiming that he
was “basically satisfied with explanations provided by the
agency and 2nd District Rep. George Arnaiz.” Currently,
there are eight contractors working for the thirteen road projects
with Bigfoot Construction undertaking three; two projects each
for Double L Construction and Development Enterprises, HLJ Construction
and Enterprises and R.C. Tagala Construction; finally, one contract
each was awarded to QM Builders, Legacy Construction, H.S. Oaminal
Construction and General Merchandise and Uy Construction and General
Merchandise.
The following is the summary of the eleven awarded
contract projects to eight construction firms including project
name and location, contract amount, contract time, contract expiry,
status of physical accomplishments: (1) QM Builders, Bais Port
Access Road, Bais City for P 19.2 million, 200 calendar days,
contract to expire on October 23, 2009, 65 percent complete; (2)
Double L Const., Dumaguete Public Market Road, P 36.4 million
280 calendar days, January 11, 2010, 65 percent complete; (3)
Bigfoot, Daro-Bunao Rd. Section, P 7.7 million, 110 calendar days,
July 25, 2009, 75 percent complete (delayed); (4) Bigfoot, San
Jose Road, P 7.7 million, 70 CD, June 15, 2009, 85 percent complete
(delayed); (5) R.C. Tagala, Tapon-Norte Tandayag Road Section,
San Jose, P 28.8 million, 200 CD, October 23, 2009, 55 percent
complete; (6) HLJ Const., Polo-Tugas, Tanjay City, P 23 million,
190 CD, October 13, 2009, 75 percent complete; (7) R.C. Tagala
Const., CAB-Sta. Cruz Road, Tanjay City, P 29 million, 200 CD,
October 23, 2009, 30 percent complete (delayed); (8) Legacy Const.,
Calo Road Section, P27 million, 200 CD, October 23, 2009, 65 percent
complete (delayed); (9) H.S. Oaminal Const., Buswang Road Section,
Amlan, P 26.3 million, 200 CD, October 23, 2009, 60 percent complete
(delayed); (10) Uy Construction and Devt., Tubtubon- Campaclan
Road Section, Sibulan, P 33.5 million, 250 CD, December 12, 2009,
60 percent complete and (11) Double L Const., Mainit-Ajong Road
Section, Sibulan, P 38.4 million, 280 CD, January 11, 2010, 60
percent complete. (by Dems Demecillo, Negros Chronicle, August
30, 2009)
View
Negros Chronicle News Clip